Abstract
The description and results of operation of the plant obtained by the expeditionary firm ″Tomsk oil gas geology″ are presented. It is shown that the use of the plant under working conditions enables to save clay powder and chemical reagent and also enables to improve the quality of the shaft and in certain cases even accelerates the process of well construction. The plant is recommended for operation both in the separate boring solutions preparation points and in centralized ones.
Original language | English |
---|---|
Pages (from-to) | 74-76 |
Number of pages | 3 |
Journal | Elektronnaya Obrabotka Materialov |
Issue number | 3 |
Publication status | Published - 1 May 1994 |
ASJC Scopus subject areas
- Electrical and Electronic Engineering